Status of 14th Apartments Venture of our Society as on 9-9-2014

A BLOCK
4th floor : Plastering work   in flat no   405
5th floor :  chejja concreting work in 501, Brick work in flat no , 502, 503, 504,506, 505, 507, 508
Terrace : paragola columns, water tank columns, lift room columns reinforcement work in progress


B BLOCK
4th floor :  2nd coat plastering work in , 401, 407
5th floor : Brick work in flat no 504, 505, 507

C BLOCK
1st floor :   1st coat plastering work in  106
2nd floor :  Brick work in flat no201,   
3rd floor:  1st coat plastering work in 304, 305 , 2nd coat plastering work in 306 and corridor area
4th floor : Brick work in flat 401, 403, 404,  

D BLOCK
Out side: 2nd coat plastering work in Ducts between 103, 104 to 503, 504, and External water lines laying in 103 to 503 flats  for Common toilets and 104 to 504
Railing : Railing fitting and finishing in flat no 203, 303,
1st floor : Toilets exhaust window finishing in flat no 106
2nd floor : Flooring tiles laying in flat 204, 205, 206
3rd floor : Kitchen platform finishing in flat no 304
5th floor : 1st coat plastering  work in flat no 508 and 2nd coat plastering work in flat no 502,507  door frames fitting in flat no 501
Internal  paper finishing in 1st and 2nd floor flats
Terrace  : Railing fitting and finishing at 303  and parapet  2nd coat plastering  work completed
Door frames : Screws fitting in  403, 404, 405, 406

E BLOCK
1st floor : Brick work  in flat no 101, 104
2nd floor : Brick work  in flat no 201,202, 203, 204, 206
4th floor :Roof slab concreting completed

F BLOCK
1st  floor : Plastering work in flat no 105, 106
2nd  floor : chejja concreting in flat no 204, Brick work  in flat no 203,204, 205, 206
3rd floor : Brick work in flat no 306,  301
Terrace : Water tank sides reinforcement work in progress

G BLOCK
1st floor : Brick work  in flat no  102, 103
4th floor : Roof slab shuttering and reinforcement work in progress


H BLOCK
3rd floor : Toilets  chipping and cleaning for water proffingin flat no 301, 302, 307, 308 and 2nd coat plastering work in flat no  303, 305, 306
4th floor : 2nd coat plastering work in flat no 403, 404, 405 , 406 and toilets floor cleaning for water proofing in flat no 401, 402, 403, 404
External :Out side jally fixing from 105 to 505 at south side

I BLOCK
Earth excavation and  marking and footing mats  & columns reinforcement work in progress

J BLOCK
Flooring  : Flooring tiles laying in flat no 305, 306, 406
1st floor : Toilets floor cleaning for water proofing in flat no 103, 104 and shelfs finishing work in flat no 103
2nd floor : Railling fitting and finishing in corridor ducts for 1st floor to 5th floors
4th floor : Door frames fitting in flat no 403, 404, 405, 406
Plumbing : WC fitting pipes  laying in flat no 405, 406, 505, 506
Painting : Outside Elevation 2nd coat painting work in progress at East side
Terrace : Paragola plastering work for pour 2 area at East side


K BLOCK
GF floor : Plastering  work in flat no  GF3,
201,202,204-Ground floor :  Brick work in progress  in flat no , 201, 203,204,
 1st floor : chejja concreting completed in  flat no 201, 202, 203, 204
301.,302,303,304: Ground floor: Brick work in flat no 301, 302, 303, 304
Terrace  floor : paragola columns reinforment work


STATUS OF 14th APARTMENTS VENTURE OF OUR SOCIETY AS ON 9-9-2014